Île-aux-Tourtes bridge: what does the reinforcement work involve?

Île-aux-Tourtes bridge: what does the reinforcement work involve?
1 / 5
Photo: Courtoisie page Facebook Maintien et reconstruction du pont de l'Île-aux-Tourtes

The third lane of the Île-aux-Tourtes bridge was reopened to traffic on January 15, following work to reinforce a damaged section of the slab. Work is currently underway to reopen additional lanes to traffic as quickly as possible. But what does the work involve? 

To read also:

Île-aux-Tourtes bridge: one lane reopened, in westbound direction only

The Ministère des Transports et de la Mobilité durable has taken to social networks, and more specifically Facebook, to provide an update on the worksite and the nature of the operations taking place there. 

According to the provincial authority, the reinforcement is carried out by installing carbon fibre-reinforced polymer (CFRP), cured after a period of curing.

To carry out the installation, several steps are required:

- A platform was installed beneath the structure, and scaffolding was erected to carry out the work. This platform is covered and heated, notably for the setting and curing of the CFRP. This is where the workers are located.

- First, the beams are repaired with concrete and mortar, while cracks are filled.

- Next, anchor holes are drilled into the beams. Drilling these holes in the right places requires meticulous precision.

- Next comes the installation of the CFRP.

- Finally, plates are manufactured in the factory according to the curvature of each girder and location, then delivered to the site to be individually inserted into the pre-drilled holes to hold the CFRP in place and reinforce the girders.

All these operations are carried out under the structure, which explains why no workers are seen on the bridge.

RECOMMANDÉS POUR VOUS

Entraves à prévoir de l’autoroute 20 à Coteau-du-lac
Travaux et CirculationPublié le 15 septembre 2026

Entraves à prévoir de l’autoroute 20 à Coteau-du-lac

Du 15 au 29 septembre, entre 21h et 6h du matin, il y aura une fermeture complète de la chaussée en direction ouest. La circulation sera déviée sur la chaussée en direction est, à contresens, avec une voie par direction. Aux mêmes dates et aux mêmes heures,  la sortie du Chemin St-Emmanuel sera complètement fermée. Les usagers seront ...

LIRE LA SUITE
Publicité

Contacter Marie-Claude Pilon