Several steps to follow

Île-aux-Tourtes bridge: what does the reinforcement work involve?

durée 13h30
24 janvier 2024
ici

commentaires

ici

likes

imprimante
Marie-Claude Pilon
email
Par Marie-Claude Pilon, Journaliste

The third lane of the Île-aux-Tourtes bridge was reopened to traffic on January 15, following work to reinforce a damaged section of the slab. Work is currently underway to reopen additional lanes to traffic as quickly as possible. But what does the work involve? 

To read also:

Île-aux-Tourtes bridge: one lane reopened, in westbound direction only

The Ministère des Transports et de la Mobilité durable has taken to social networks, and more specifically Facebook, to provide an update on the worksite and the nature of the operations taking place there. 

According to the provincial authority, the reinforcement is carried out by installing carbon fibre-reinforced polymer (CFRP), cured after a period of curing.

To carry out the installation, several steps are required:

- A platform was installed beneath the structure, and scaffolding was erected to carry out the work. This platform is covered and heated, notably for the setting and curing of the CFRP. This is where the workers are located.

- First, the beams are repaired with concrete and mortar, while cracks are filled.

- Next, anchor holes are drilled into the beams. Drilling these holes in the right places requires meticulous precision.

- Next comes the installation of the CFRP.

- Finally, plates are manufactured in the factory according to the curvature of each girder and location, then delivered to the site to be individually inserted into the pre-drilled holes to hold the CFRP in place and reinforce the girders.

All these operations are carried out under the structure, which explains why no workers are seen on the bridge.

RECOMMANDÉS POUR VOUS


Publié à 6h00

Fermeture complète du boulevard Perrot le lundi 4 mai

La Ville de Notre-Dame-de l'Île-Perrot avise les usagers de la route de la fermeture complète du boulevard Perrot, à l'intersection de Grande-Anse, le lundi 4 mai de 7 h à 17 h.  Plus précisément, la fermeture aura lieu entre les numéros civiques 1477 et 1483, boulevard Perrot pour permettre les travaux de raccordement au réseau d’aqueduc et ...

Publié le 30 avril 2026

Entrave sur la route 132 à Salaberry-de-Valleyfield

Le Ministère des Transports et de la Mobilité durable (MTMD) avise les usagers de la route de la mise en place d'une entrave sur la route 132, à Salaberry-de-Valleyfield. Plus précisément, depuis 9 h le jeudi 30 avril jusqu'au vendredi 1er mai à 15 h, la circulation se fera en alternance sur le boulevard Hébert, sur le pont de la rivière ...

Publié le 29 avril 2026

Travaux de forage en cours sur la route 338

Le ministère des transports et de la mobilité durable (MTMD) informe les automobilistes d’une entrave mineure sur la route 338 à Coteau-du-Lac. Les travaux routiers seront effectués entre le 28 avril et le 5 mai. Tout au long de cette période, une seule voie est accessible sur la portion de la route 338 entre les rues Provost et Guy-Lauzon. En ...

app-store-badge google-play-badge