Nous joindre
X
Rechercher
Publicité

Ministry of Transport and Sustainable Mobility

Île-aux-Tourtes bridge: the Autorité des marchés publics draws up a poor assessment

durée 08h26
3 novembre 2023
ici

commentaires

ici

likes

 

vues

imprimante
Jessica Brisson
email
Par Jessica Brisson, Éditrice adjointe

Deficiencies in the management and planning of contracts, lack of documentation, communication problems, failure to comply with recommendations - in short, the Autorité des marchés publics (AMP) has drawn up a bleak picture of the Ministry of Transport and Sustainable Mobility (MTSM) contract management in the Île-aux-Tourtes bridge case.

In its latest report, published on Wednesday, the AMP highlighted a series of shortcomings in the management and planning of contracts for the maintenance and upkeep of the current structure of the Île-aux-Tourtes bridge.

As a result, MTSM was unable to carry out the necessary work in a timely manner. 

According to the report, the MTSM ignored some 35 notices indicating that the construction contractor, Roxboro Excavation Inc. was not complying with the manufacturer's recommendations, particularly with regard to mortar preparation.

Also according to the AMP report, on May 8, 2020, the Ministère gave the contractor the mandate to carry out maintenance work. Although the specifications called for the use of 400 liters of cementitious mortar, the AMP's examination revealed that the work was not carried out as required.

"However, from the very first preparation work, the quantity of mortar used reached 4,000 liters. Due to issues with the mortar preparation used, the 4,000 liters spread had to be removed. In all, 8,000 liters were needed to complete the work, resulting in an additional expenditure of $4.938 million, excluding the cost of the mortar," reads the 130-page document.

Among the other shortcomings noted by the AMP in the Île-aux-Tourtes bridge file are the lack of visits by the MTSM to the worksite, the lack of communication between the various stakeholders, the disappearance and non-reading of certain e-mails, the unavailability of certain documents, and more.

Roxboro Excavation Inc. is part of the consortium formed by Dragados Canada Inc. Roxboro Excavation Inc. and Construction DeMathieu Bard (CDB) Inc. and was awarded the contract to build the new infrastructure, scheduled for partial inauguration in 2026.

The full report is available at https://amp.quebec.

commentairesCommentaires

0

Pour partager votre opinion vous devez être connecté.

RECOMMANDÉS POUR VOUS


Fermeture à prévoir sur l'autoroute 30

Des travaux d'entretien forceront la fermeture complète de la bretelle de la sortie 29 de l'autoroute 20 est vers l'autoroute 30 à Vaudreuil-Dorion, dès 20h le 16 mars, et ce, jusqu'au 17 mars, 6h. Les détours suivants seront mis en place:  - A30 Ouest A20 est; Gauche sur Rte Hardwood en direction ouest; Gauche sur Rue Henry-Ford en ...

Le pont piéton du parc Thomas-Monroe sera finalement réparé

Après avoir refusé d'acquitter la facture des travaux d'urgence permettant de réparer un pont piéton situé sur le territoire municipal dont l'état est jugé préoccupant, la Ville de Coteau-du-Lac a finalement accepté. C'est lors de la séance régulière du 11 mars dernier que la mairesse Andrée Brosseau a utilisé son droit de veto afin que la ...

Une citoyenne de Rigaud déplore une récente décision de l'administration municipale

Une citoyenne de Rigaud qui avait pour habitude de stationner sa voiture, la nuit, dans le stationnement la bibliothèque municipale déplore un changement de réglementation passé sous silence par la municipalité. Elle a dû payer 60$ pour l'apprendre à ses dépends.  « Je demeure sur la rue Saint-Pierre dans un appartement et c'est très clair dans ...

app-store-badge google-play-badge