Nous joindre
X
Rechercher
Publicité

Ministry of Transport and Sustainable Mobility

Île-aux-Tourtes bridge: the Autorité des marchés publics draws up a poor assessment

durée 08h26
3 novembre 2023
ici

commentaires

ici

likes

imprimante
Jessica Brisson
Par Jessica Brisson, Éditrice adjointe

Deficiencies in the management and planning of contracts, lack of documentation, communication problems, failure to comply with recommendations - in short, the Autorité des marchés publics (AMP) has drawn up a bleak picture of the Ministry of Transport and Sustainable Mobility (MTSM) contract management in the Île-aux-Tourtes bridge case.

In its latest report, published on Wednesday, the AMP highlighted a series of shortcomings in the management and planning of contracts for the maintenance and upkeep of the current structure of the Île-aux-Tourtes bridge.

As a result, MTSM was unable to carry out the necessary work in a timely manner. 

According to the report, the MTSM ignored some 35 notices indicating that the construction contractor, Roxboro Excavation Inc. was not complying with the manufacturer's recommendations, particularly with regard to mortar preparation.

Also according to the AMP report, on May 8, 2020, the Ministère gave the contractor the mandate to carry out maintenance work. Although the specifications called for the use of 400 liters of cementitious mortar, the AMP's examination revealed that the work was not carried out as required.

"However, from the very first preparation work, the quantity of mortar used reached 4,000 liters. Due to issues with the mortar preparation used, the 4,000 liters spread had to be removed. In all, 8,000 liters were needed to complete the work, resulting in an additional expenditure of $4.938 million, excluding the cost of the mortar," reads the 130-page document.

Among the other shortcomings noted by the AMP in the Île-aux-Tourtes bridge file are the lack of visits by the MTSM to the worksite, the lack of communication between the various stakeholders, the disappearance and non-reading of certain e-mails, the unavailability of certain documents, and more.

Roxboro Excavation Inc. is part of the consortium formed by Dragados Canada Inc. Roxboro Excavation Inc. and Construction DeMathieu Bard (CDB) Inc. and was awarded the contract to build the new infrastructure, scheduled for partial inauguration in 2026.

The full report is available at https://amp.quebec.

RECOMMANDÉS POUR VOUS


Publié le 17 juillet 2026

Un tronçon de la rue des Érables deviendra à double sens

La Ville de L'Île-Perrot informe ses citoyens que le tronçon de la rue des Érables situé entre la 23e Avenue et la 24e Avenue sera à double sens dès le 30 juillet 2026.  Cette mesure découle des gains en fluidité réalisés sur le territoire ces dernières années.  En effet, les interventions concrètes suivantes, prévues au plan directeur, ont ...

Publié le 13 juillet 2026

Travaux de pavage prévus le lundi 13 juillet à Rigaud

La Ville de Rigaud avise ses citoyens que des travaux de pavage sont prévus le lundi 13 juillet sur la rue Saint-Pierre afin d’asphalter la tranchée. Les automobilistes peuvent s’attendre à de la circulation en alternance, gérée par des signaleurs ou des feux de circulation temporaires. Les travaux pourraient être reportés en cas de conditions ...

Publié le 6 juillet 2026

Entraves routières sur la 34e avenue et la 20e rue à Saint-Zotique

La Ville de Saint-Zotique souhaite informer les citoyens que des travaux de branchement d’aqueduc de la nouvelle 30ᵉ avenue auront lieu sur un tronçon de la 34ᵉ avenue et de la 20ᵉ rue, du 6 au 9 juillet 2026. Durant cette période, des entraves importantes à la circulation sont à prévoir : Les 6-7 et 9 juillet, il y aura fermeture complète de ...

app-store-badge google-play-badge