Nous joindre
X
Rechercher
Publicité

Ministry of Transport and Sustainable Mobility

Île-aux-Tourtes bridge: the Autorité des marchés publics draws up a poor assessment

durée 08h26
3 novembre 2023
ici

commentaires

ici

likes

imprimante
Jessica Brisson
email
Par Jessica Brisson, Éditrice adjointe

Deficiencies in the management and planning of contracts, lack of documentation, communication problems, failure to comply with recommendations - in short, the Autorité des marchés publics (AMP) has drawn up a bleak picture of the Ministry of Transport and Sustainable Mobility (MTSM) contract management in the Île-aux-Tourtes bridge case.

In its latest report, published on Wednesday, the AMP highlighted a series of shortcomings in the management and planning of contracts for the maintenance and upkeep of the current structure of the Île-aux-Tourtes bridge.

As a result, MTSM was unable to carry out the necessary work in a timely manner. 

According to the report, the MTSM ignored some 35 notices indicating that the construction contractor, Roxboro Excavation Inc. was not complying with the manufacturer's recommendations, particularly with regard to mortar preparation.

Also according to the AMP report, on May 8, 2020, the Ministère gave the contractor the mandate to carry out maintenance work. Although the specifications called for the use of 400 liters of cementitious mortar, the AMP's examination revealed that the work was not carried out as required.

"However, from the very first preparation work, the quantity of mortar used reached 4,000 liters. Due to issues with the mortar preparation used, the 4,000 liters spread had to be removed. In all, 8,000 liters were needed to complete the work, resulting in an additional expenditure of $4.938 million, excluding the cost of the mortar," reads the 130-page document.

Among the other shortcomings noted by the AMP in the Île-aux-Tourtes bridge file are the lack of visits by the MTSM to the worksite, the lack of communication between the various stakeholders, the disappearance and non-reading of certain e-mails, the unavailability of certain documents, and more.

Roxboro Excavation Inc. is part of the consortium formed by Dragados Canada Inc. Roxboro Excavation Inc. and Construction DeMathieu Bard (CDB) Inc. and was awarded the contract to build the new infrastructure, scheduled for partial inauguration in 2026.

The full report is available at https://amp.quebec.

RECOMMANDÉS POUR VOUS


Publié le 26 novembre 2025

Fermeture d'une voie sur deux de l'autoroute 20

Québec 511 rappelle des travaux sur l’autoroute 20 à Saint-Zotique et à Rivière-Beaudette ce mercredi 26 novembre. Les interventions entraineront la fermeture d’une voie sur deux, et ce jusqu’à 18 h. Bien que l'entrave soit considérée comme mineure, les travaux, indiqués comme une inspection de la structure, dureront jusqu'à 15h ...

Publié le 26 novembre 2025

L'avenue Ranger bloquée de mercredi à jeudi

Une entrave aura lieu sur l'avenue Ranger à Vaudreuil-Dorion de ce mercredi 26 novembre à 7 h au vendredi 28 novembre à 17 h. Les travaux viseront à paver l'intersection avec la rue Chicoine. Pendant cette période, la bretelle d’accès Ranger Sud vers l’A-20 Ouest sera complètement fermée, de même que l’intersection Ranger entre l’autoroute 20 et ...

Publié le 25 novembre 2025

Entrave sur le chemin du Fleuve

Dès mercredi 26 novembre, le service de transport ferroviaire (CN) réalisera des travaux sur le viaduc situé près de l’adresse du 53 chemin du Fleuve. Les travaux jugés mineurs ne devraient pas s'étaler sur plus d’une journée. À moins de perturbations météo qui pourraient faire en sorte que l’entrave s'éternise, les travaux commenceront à partir ...

app-store-badge google-play-badge