Ministry of Transport and Sustainable Mobility
Île-aux-Tourtes bridge: the Autorité des marchés publics draws up a poor assessment
Deficiencies in the management and planning of contracts, lack of documentation, communication problems, failure to comply with recommendations - in short, the Autorité des marchés publics (AMP) has drawn up a bleak picture of the Ministry of Transport and Sustainable Mobility (MTSM) contract management in the Île-aux-Tourtes bridge case.
In its latest report, published on Wednesday, the AMP highlighted a series of shortcomings in the management and planning of contracts for the maintenance and upkeep of the current structure of the Île-aux-Tourtes bridge.
As a result, MTSM was unable to carry out the necessary work in a timely manner.
According to the report, the MTSM ignored some 35 notices indicating that the construction contractor, Roxboro Excavation Inc. was not complying with the manufacturer's recommendations, particularly with regard to mortar preparation.
Also according to the AMP report, on May 8, 2020, the Ministère gave the contractor the mandate to carry out maintenance work. Although the specifications called for the use of 400 liters of cementitious mortar, the AMP's examination revealed that the work was not carried out as required.
"However, from the very first preparation work, the quantity of mortar used reached 4,000 liters. Due to issues with the mortar preparation used, the 4,000 liters spread had to be removed. In all, 8,000 liters were needed to complete the work, resulting in an additional expenditure of $4.938 million, excluding the cost of the mortar," reads the 130-page document.
Among the other shortcomings noted by the AMP in the Île-aux-Tourtes bridge file are the lack of visits by the MTSM to the worksite, the lack of communication between the various stakeholders, the disappearance and non-reading of certain e-mails, the unavailability of certain documents, and more.
Roxboro Excavation Inc. is part of the consortium formed by Dragados Canada Inc. Roxboro Excavation Inc. and Construction DeMathieu Bard (CDB) Inc. and was awarded the contract to build the new infrastructure, scheduled for partial inauguration in 2026.
The full report is available at https://amp.quebec.
RECOMMANDÉS POUR VOUS

Des travaux d'asphaltage entraîneront des entraves à Coteau-du-Lac
Du 4 au 8 octobre, entre 21h et 6h du matin, il y aura une fermeture complète de la chaussée en direction ouest sur l'autoroute 20 à Coteau-du-Lac entre les kilomètres 16 et 18. La circulation sera déviée sur la chaussée en direction est, à contresens, avec une voie par direction. Cette entrave est requise en raison de travaux ...
LIRE LA SUITE
Entrave du 5 au 15 octobre à Sainte-Anne-de-Bellevue
La Ville de Sainte-Anne-de-Bellevue avise ses citoyens de la tenue de travaux par l'entrepreneur G-TEK Inc qui se tiendront du 5 au 15 octobre au niveau de la sortie 41 du chemin de service. Mandaté par Hydro-Québec, le chantier prendra place en direction ouest. Durant celui-ci, il y aura: - Fermeture complète de la voie de service nord de ...
LIRE LA SUITE
Les Québécois sont-ils vraiment des bons conducteurs?
Les Québécois sont-ils aussi prudents au volant qu’ils le pensent? À l’occasion de la 3ème édition de la Semaine de la bonne conduite, Tecnic dévoile les premiers résultats du Baromètre Tecnic, disponible sur le tout nouveau Hub Tecnic, une initiative annuelle réalisée avec la firme Léger pour suivre l’évolution des perceptions et ...
LIRE LA SUITE
