Ministry of Transport and Sustainable Mobility
Île-aux-Tourtes bridge: the Autorité des marchés publics draws up a poor assessment
Deficiencies in the management and planning of contracts, lack of documentation, communication problems, failure to comply with recommendations - in short, the Autorité des marchés publics (AMP) has drawn up a bleak picture of the Ministry of Transport and Sustainable Mobility (MTSM) contract management in the Île-aux-Tourtes bridge case.
In its latest report, published on Wednesday, the AMP highlighted a series of shortcomings in the management and planning of contracts for the maintenance and upkeep of the current structure of the Île-aux-Tourtes bridge.
As a result, MTSM was unable to carry out the necessary work in a timely manner.
According to the report, the MTSM ignored some 35 notices indicating that the construction contractor, Roxboro Excavation Inc. was not complying with the manufacturer's recommendations, particularly with regard to mortar preparation.
Also according to the AMP report, on May 8, 2020, the Ministère gave the contractor the mandate to carry out maintenance work. Although the specifications called for the use of 400 liters of cementitious mortar, the AMP's examination revealed that the work was not carried out as required.
"However, from the very first preparation work, the quantity of mortar used reached 4,000 liters. Due to issues with the mortar preparation used, the 4,000 liters spread had to be removed. In all, 8,000 liters were needed to complete the work, resulting in an additional expenditure of $4.938 million, excluding the cost of the mortar," reads the 130-page document.
Among the other shortcomings noted by the AMP in the Île-aux-Tourtes bridge file are the lack of visits by the MTSM to the worksite, the lack of communication between the various stakeholders, the disappearance and non-reading of certain e-mails, the unavailability of certain documents, and more.
Roxboro Excavation Inc. is part of the consortium formed by Dragados Canada Inc. Roxboro Excavation Inc. and Construction DeMathieu Bard (CDB) Inc. and was awarded the contract to build the new infrastructure, scheduled for partial inauguration in 2026.
The full report is available at https://amp.quebec.
RECOMMANDÉS POUR VOUS

Travaux en cours au parc Godin à Sainte-Anne-de-Bellevue
La Ville de Sainte-Anne-de-Bellevue avise ses citoyens qu'à compter du 15 octobre, le chalet Famille de Chantal du parc Godin sera temporairement fermé pour une durée approximative de trois semaines pour des travaux de rénovation des salles de bains. Les travaux se tiendront de 7 h à 17 h. Durant cette période, le parc Godin demeurera ...
LIRE LA SUITE
Une fermeture de la sortie no 41 de l’A-40 en direction est à venir
Le ministère des Transports et de la Mobilité durable informe les usagers de la route que la sortie n° 41 (Sainte-Anne-de-Bellevue, boulevard des Anciens-Combattants) de l’autoroute 40 en direction est sera complètement fermée du 16 au 17 octobre. Cette entrave est requise afin de transférer la circulation sur la voie de desserte finale de ...
LIRE LA SUITE
Fermeture en cours sur la route 340 à Saint-Clet et Saint-Lazare
Le ministère des Transports et de la mobilité durable (MTMD) avise les usagers de la route de la tenue d'une entrave jusqu'au 17 octobre sur la route 340, entre les chemins Saint-Dominique et Saint-Emmanuel, à Saint-Clet et Coteau-du-Lac. Celle-ci est nécessaire pour permettre la réfection d'un ponceau. Durant ce chantier, le tronçon cité ...
LIRE LA SUITE
