Nous joindre
X
Rechercher
Publicité

Ministry of Transport and Sustainable Mobility

Île-aux-Tourtes bridge: the Autorité des marchés publics draws up a poor assessment

durée 08h26
3 novembre 2023
ici

commentaires

ici

likes

 

vues

imprimante
Jessica Brisson
email
Par Jessica Brisson, Éditrice adjointe

Deficiencies in the management and planning of contracts, lack of documentation, communication problems, failure to comply with recommendations - in short, the Autorité des marchés publics (AMP) has drawn up a bleak picture of the Ministry of Transport and Sustainable Mobility (MTSM) contract management in the Île-aux-Tourtes bridge case.

In its latest report, published on Wednesday, the AMP highlighted a series of shortcomings in the management and planning of contracts for the maintenance and upkeep of the current structure of the Île-aux-Tourtes bridge.

As a result, MTSM was unable to carry out the necessary work in a timely manner. 

According to the report, the MTSM ignored some 35 notices indicating that the construction contractor, Roxboro Excavation Inc. was not complying with the manufacturer's recommendations, particularly with regard to mortar preparation.

Also according to the AMP report, on May 8, 2020, the Ministère gave the contractor the mandate to carry out maintenance work. Although the specifications called for the use of 400 liters of cementitious mortar, the AMP's examination revealed that the work was not carried out as required.

"However, from the very first preparation work, the quantity of mortar used reached 4,000 liters. Due to issues with the mortar preparation used, the 4,000 liters spread had to be removed. In all, 8,000 liters were needed to complete the work, resulting in an additional expenditure of $4.938 million, excluding the cost of the mortar," reads the 130-page document.

Among the other shortcomings noted by the AMP in the Île-aux-Tourtes bridge file are the lack of visits by the MTSM to the worksite, the lack of communication between the various stakeholders, the disappearance and non-reading of certain e-mails, the unavailability of certain documents, and more.

Roxboro Excavation Inc. is part of the consortium formed by Dragados Canada Inc. Roxboro Excavation Inc. and Construction DeMathieu Bard (CDB) Inc. and was awarded the contract to build the new infrastructure, scheduled for partial inauguration in 2026.

The full report is available at https://amp.quebec.

commentairesCommentaires

0

Pour partager votre opinion vous devez être connecté.

RECOMMANDÉS POUR VOUS


Congé des Fêtes: la gestion dynamique reste en place

Le long congé des Fêtes arrive à grands pas et le Ministère des Transports et de la Mobilité durable fait le point sur la configuration en place sur le pont de l'Île-aux-Tourtes pendant cette période.  En rappel, à l’exception de la période entre le 25 décembre et le 2 janvier, la gestion dynamique des trois voies de circulation demeure active ...

19 décembre 2024

Fermeture du pont de l'Île-aux-Tourtes cette nuit

Le ministère des Transports et de la mobilité durable annonce la fermeture de nuit du pont de l'Île-aux-Tourtes dès ce jeudi 19 décembre 23h59 au vendredi 20 décembre à 5h am.  L'entrave prendra place sur l'autoroute 40 , en direction est, entre la sortie no 35 - Saint-Charles et le boulevard des Anciens-Combattants. Elle sera requise afin de ...

17 décembre 2024

Coteau-du-Lac s'entend avec le CN pour sécuriser un tronçon cyclable

Les élus de la Ville de Coteau-du-Lac ont profité de leur dernière réunion régulière de l'année 2024 pour donner leur aval à un projet attendu sur le territoire municipal. Celui-ci consistera à finaliser un nouveau tronçon de piste cyclable situé derrière la piscine municipale.  D'ailleurs, la Ville paraphe les derniers détails d'une convention ...

app-store-badge google-play-badge