Ministry of Transport and Sustainable Mobility
Île-aux-Tourtes bridge: the Autorité des marchés publics draws up a poor assessment
Deficiencies in the management and planning of contracts, lack of documentation, communication problems, failure to comply with recommendations - in short, the Autorité des marchés publics (AMP) has drawn up a bleak picture of the Ministry of Transport and Sustainable Mobility (MTSM) contract management in the Île-aux-Tourtes bridge case.
In its latest report, published on Wednesday, the AMP highlighted a series of shortcomings in the management and planning of contracts for the maintenance and upkeep of the current structure of the Île-aux-Tourtes bridge.
As a result, MTSM was unable to carry out the necessary work in a timely manner.
According to the report, the MTSM ignored some 35 notices indicating that the construction contractor, Roxboro Excavation Inc. was not complying with the manufacturer's recommendations, particularly with regard to mortar preparation.
Also according to the AMP report, on May 8, 2020, the Ministère gave the contractor the mandate to carry out maintenance work. Although the specifications called for the use of 400 liters of cementitious mortar, the AMP's examination revealed that the work was not carried out as required.
"However, from the very first preparation work, the quantity of mortar used reached 4,000 liters. Due to issues with the mortar preparation used, the 4,000 liters spread had to be removed. In all, 8,000 liters were needed to complete the work, resulting in an additional expenditure of $4.938 million, excluding the cost of the mortar," reads the 130-page document.
Among the other shortcomings noted by the AMP in the Île-aux-Tourtes bridge file are the lack of visits by the MTSM to the worksite, the lack of communication between the various stakeholders, the disappearance and non-reading of certain e-mails, the unavailability of certain documents, and more.
Roxboro Excavation Inc. is part of the consortium formed by Dragados Canada Inc. Roxboro Excavation Inc. and Construction DeMathieu Bard (CDB) Inc. and was awarded the contract to build the new infrastructure, scheduled for partial inauguration in 2026.
The full report is available at https://amp.quebec.
RECOMMANDÉS POUR VOUS

Des travaux de réparations ponctuelles du réseau sanitaire à venir à NDIP
La Ville de Notre-Dame-de-l'Île-Perrot informe ses citoyens que des travaux de réparations ponctuelles du réseau sanitaire auront lieu dans certains secteurs à compter du 13 octobre. Les rues visées par ces chantiers temporaires sont les suivantes: - Rue Robillard; - Rue Rollinet; - Rue Carrière; - Rue Pierre-Ricard; - Rue Rémillard; - Rue ...
LIRE LA SUITE
Fermeture de l'autoroute 40 à Senneville ce jeudi en soirée
Le ministère des Transports et de la Mobilité durable informe les usagers de la route que l’autoroute 40 en direction est sera fermée durant la nuit du 8 au 9 octobre. Cette entrave est requise pour des travaux de colmatage de joints. Le pont de l’Île-aux-Tourtes demeurera ouvert durant les travaux. Entrave à la circulation Durant ces ...
LIRE LA SUITE
Des travaux d'asphaltage entraîneront des entraves à Coteau-du-Lac
Du 4 au 8 octobre, entre 21h et 6h du matin, il y aura une fermeture complète de la chaussée en direction ouest sur l'autoroute 20 à Coteau-du-Lac entre les kilomètres 16 et 18. La circulation sera déviée sur la chaussée en direction est, à contresens, avec une voie par direction. Cette entrave est requise en raison de travaux ...
LIRE LA SUITE
