Nous joindre
X
Rechercher
Publicité

Ministry of Transport and Sustainable Mobility

Île-aux-Tourtes bridge: the Autorité des marchés publics draws up a poor assessment

durée 08h26
3 novembre 2023
ici

commentaires

ici

likes

imprimante
Jessica Brisson
Par Jessica Brisson, Éditrice adjointe

Deficiencies in the management and planning of contracts, lack of documentation, communication problems, failure to comply with recommendations - in short, the Autorité des marchés publics (AMP) has drawn up a bleak picture of the Ministry of Transport and Sustainable Mobility (MTSM) contract management in the Île-aux-Tourtes bridge case.

In its latest report, published on Wednesday, the AMP highlighted a series of shortcomings in the management and planning of contracts for the maintenance and upkeep of the current structure of the Île-aux-Tourtes bridge.

As a result, MTSM was unable to carry out the necessary work in a timely manner. 

According to the report, the MTSM ignored some 35 notices indicating that the construction contractor, Roxboro Excavation Inc. was not complying with the manufacturer's recommendations, particularly with regard to mortar preparation.

Also according to the AMP report, on May 8, 2020, the Ministère gave the contractor the mandate to carry out maintenance work. Although the specifications called for the use of 400 liters of cementitious mortar, the AMP's examination revealed that the work was not carried out as required.

"However, from the very first preparation work, the quantity of mortar used reached 4,000 liters. Due to issues with the mortar preparation used, the 4,000 liters spread had to be removed. In all, 8,000 liters were needed to complete the work, resulting in an additional expenditure of $4.938 million, excluding the cost of the mortar," reads the 130-page document.

Among the other shortcomings noted by the AMP in the Île-aux-Tourtes bridge file are the lack of visits by the MTSM to the worksite, the lack of communication between the various stakeholders, the disappearance and non-reading of certain e-mails, the unavailability of certain documents, and more.

Roxboro Excavation Inc. is part of the consortium formed by Dragados Canada Inc. Roxboro Excavation Inc. and Construction DeMathieu Bard (CDB) Inc. and was awarded the contract to build the new infrastructure, scheduled for partial inauguration in 2026.

The full report is available at https://amp.quebec.

RECOMMANDÉS POUR VOUS


Publié hier à 15h00

Réaménagement de la route 340: fermeture complète à prévoir

Le ministère des Transports et de la Mobilité durable (MTMD) informe la population qu’un changement de phase entraînera la fermeture complète d’une portion du boulevard de la Cité-des-Jeunes (route 340) et d’une bretelle de l’autoroute 30 (de l’Acier), en direction ouest, à la hauteur de la route 340, à Vaudreuil-Dorion.  Cette entrave est ...

Publié hier à 8h00

Entrave majeure sur la rue Émile-Bouchard à Vaudreuil-Dorion

La ville de Vaudreuil-Dorion a récemment annoncé la fermeture complète de la rue Émile-Bouchard entre les rues Édouard‑Lalonde et Phil‑Goyette pour une période de quatre jour. L'entrave à débuter à compter de 7 h le mardi 16 juin.  Les travaux, requis pour un branchement de service devrait être achevé le vendredi 19 h juin vers 17 h. La Ville ...

Publié hier à 6h00

Rappel de la fermeture de la rue Principale à Saint-Zotique

Nécessaire en vue de la construction d'un nouveau trottoir, la rue Principale, entre la 37ᵉ avenue et l'avenue des Maîtres, est fermée depuis le mercredi 15 juin à Saint-Zotique. Les travaux dureront une bonne partie du mois, soit jusqu'au 26 juin en soirée. La circulation se fait en alternance du lundi au vendredi entre 7 h et 18 h. Des chemins ...

app-store-badge google-play-badge