Nous joindre
X
Rechercher
Publicité

Ministry of Transport and Sustainable Mobility

Île-aux-Tourtes bridge: the Autorité des marchés publics draws up a poor assessment

durée 08h26
3 novembre 2023
ici

commentaires

ici

likes

imprimante
Jessica Brisson
email
Par Jessica Brisson, Éditrice adjointe

Deficiencies in the management and planning of contracts, lack of documentation, communication problems, failure to comply with recommendations - in short, the Autorité des marchés publics (AMP) has drawn up a bleak picture of the Ministry of Transport and Sustainable Mobility (MTSM) contract management in the Île-aux-Tourtes bridge case.

In its latest report, published on Wednesday, the AMP highlighted a series of shortcomings in the management and planning of contracts for the maintenance and upkeep of the current structure of the Île-aux-Tourtes bridge.

As a result, MTSM was unable to carry out the necessary work in a timely manner. 

According to the report, the MTSM ignored some 35 notices indicating that the construction contractor, Roxboro Excavation Inc. was not complying with the manufacturer's recommendations, particularly with regard to mortar preparation.

Also according to the AMP report, on May 8, 2020, the Ministère gave the contractor the mandate to carry out maintenance work. Although the specifications called for the use of 400 liters of cementitious mortar, the AMP's examination revealed that the work was not carried out as required.

"However, from the very first preparation work, the quantity of mortar used reached 4,000 liters. Due to issues with the mortar preparation used, the 4,000 liters spread had to be removed. In all, 8,000 liters were needed to complete the work, resulting in an additional expenditure of $4.938 million, excluding the cost of the mortar," reads the 130-page document.

Among the other shortcomings noted by the AMP in the Île-aux-Tourtes bridge file are the lack of visits by the MTSM to the worksite, the lack of communication between the various stakeholders, the disappearance and non-reading of certain e-mails, the unavailability of certain documents, and more.

Roxboro Excavation Inc. is part of the consortium formed by Dragados Canada Inc. Roxboro Excavation Inc. and Construction DeMathieu Bard (CDB) Inc. and was awarded the contract to build the new infrastructure, scheduled for partial inauguration in 2026.

The full report is available at https://amp.quebec.

RECOMMANDÉS POUR VOUS


Publié à 13h00

Plusieurs accidents sur les routes de la région

En ce lundi 26 janvier, la Sûreté du Québec (SQ) dénombre déjà de nombreux accident sur le réseaux routier et la région de Vaudreuil-Soulanges n'est pas épargné. Les véhicules de déneigement font de leur mieux pour dégager les routes, mais les automobilistes se doivent quand même de rester prudent et de surveiller leur vitesse. Ainsi, il est ...

Publié à 10h00

Des travaux de nuit prévus dans le secteur Frontenac à Saint-Lazare

La Ville de Saint-Lazare avise les usagers de la route de son territoire de la tenue de travaux de nuit sur plusieurs rues du secteur Frontenac. Le chantier se tiendra du lundi 26 au mardi 27 janvier de 19h à 4h am, puis du mercredi 28 janvier au jeudi 29 janvier selon le même horaire.  La première phase se tiendra sur la route de la ...

Publié le 24 janvier 2026

Le pont de glace Hudson-Oka est réouvert

Le pont de glace permettant le passage des autos de Hudson à Oka est de nouveau ouvert depuis le 21 janvier en matinée. Les températures plus douces des dernières semaines jumelées au niveau de l'eau anormalement bas avaient poussé le groupe qui opère la traversée à fermer le pont de glace pour des questions de sécurité. « Ça pique la curiosité ...

app-store-badge google-play-badge