Nous joindre
X
Rechercher
Publicité

Ministry of Transport and Sustainable Mobility

Île-aux-Tourtes bridge: the Autorité des marchés publics draws up a poor assessment

durée 08h26
3 novembre 2023
ici

commentaires

ici

likes

 

vues

imprimante
Jessica Brisson
email
Par Jessica Brisson, Éditrice adjointe

Deficiencies in the management and planning of contracts, lack of documentation, communication problems, failure to comply with recommendations - in short, the Autorité des marchés publics (AMP) has drawn up a bleak picture of the Ministry of Transport and Sustainable Mobility (MTSM) contract management in the Île-aux-Tourtes bridge case.

In its latest report, published on Wednesday, the AMP highlighted a series of shortcomings in the management and planning of contracts for the maintenance and upkeep of the current structure of the Île-aux-Tourtes bridge.

As a result, MTSM was unable to carry out the necessary work in a timely manner. 

According to the report, the MTSM ignored some 35 notices indicating that the construction contractor, Roxboro Excavation Inc. was not complying with the manufacturer's recommendations, particularly with regard to mortar preparation.

Also according to the AMP report, on May 8, 2020, the Ministère gave the contractor the mandate to carry out maintenance work. Although the specifications called for the use of 400 liters of cementitious mortar, the AMP's examination revealed that the work was not carried out as required.

"However, from the very first preparation work, the quantity of mortar used reached 4,000 liters. Due to issues with the mortar preparation used, the 4,000 liters spread had to be removed. In all, 8,000 liters were needed to complete the work, resulting in an additional expenditure of $4.938 million, excluding the cost of the mortar," reads the 130-page document.

Among the other shortcomings noted by the AMP in the Île-aux-Tourtes bridge file are the lack of visits by the MTSM to the worksite, the lack of communication between the various stakeholders, the disappearance and non-reading of certain e-mails, the unavailability of certain documents, and more.

Roxboro Excavation Inc. is part of the consortium formed by Dragados Canada Inc. Roxboro Excavation Inc. and Construction DeMathieu Bard (CDB) Inc. and was awarded the contract to build the new infrastructure, scheduled for partial inauguration in 2026.

The full report is available at https://amp.quebec.

RECOMMANDÉS POUR VOUS


Publié le 5 novembre 2025

Fermeture de l'autoroute 20 en direction ouest à Vaudreuil-Dorion

En raison d'une violente collision impliquant deux poids lourds survenue plus tôt ce mercredi 5 novembre en matinée, l'autoroute 20 est fermée pour les prochaines heures à Vaudreuil-Dorion. Plus spécifiquement, la fermeture est en direction ouest entre la route 340 et la hauteur de la route 342.  L'accident est survenu vers 6h ce matin sur ...

Publié le 5 novembre 2025

Travaux d’inspection sur l’autoroute 40 à Rigaud

Le ministère des Transports et de la Mobilité durable (MTMD) procédera à des travaux d’inspection sur l’autoroute 40, à la hauteur de la route 342, à Rigaud, le jeudi 6 novembre. L’intervention entraînera la fermeture d’une voie sur deux, dans les directions est et ouest, de 7 h à 16 h. De plus, l’entrée de la rue Jean-Marc-Séguin vers ...

Publié le 4 novembre 2025

Travaux devancés au passage à niveau du chemin St-Thomas

La Ville de Saint-Zotique avise la population que les travaux initialement prévus le jeudi 6 novembre 2025 ont été devancés et se déroulent plutôt aujourd’hui, mardi 4 novembre, en raison d’un ajustement de planification. Les travaux visent la mise à niveau et le resurfaçage de la voie ferrée au passage à niveau du chemin St-Thomas, à ...

app-store-badge google-play-badge