Nous joindre
X
Rechercher
Publicité

Ministry of Transport and Sustainable Mobility

Île-aux-Tourtes bridge: the Autorité des marchés publics draws up a poor assessment

durée 08h26
3 novembre 2023
ici

commentaires

ici

likes

imprimante
Jessica Brisson
email
Par Jessica Brisson, Éditrice adjointe

Deficiencies in the management and planning of contracts, lack of documentation, communication problems, failure to comply with recommendations - in short, the Autorité des marchés publics (AMP) has drawn up a bleak picture of the Ministry of Transport and Sustainable Mobility (MTSM) contract management in the Île-aux-Tourtes bridge case.

In its latest report, published on Wednesday, the AMP highlighted a series of shortcomings in the management and planning of contracts for the maintenance and upkeep of the current structure of the Île-aux-Tourtes bridge.

As a result, MTSM was unable to carry out the necessary work in a timely manner. 

According to the report, the MTSM ignored some 35 notices indicating that the construction contractor, Roxboro Excavation Inc. was not complying with the manufacturer's recommendations, particularly with regard to mortar preparation.

Also according to the AMP report, on May 8, 2020, the Ministère gave the contractor the mandate to carry out maintenance work. Although the specifications called for the use of 400 liters of cementitious mortar, the AMP's examination revealed that the work was not carried out as required.

"However, from the very first preparation work, the quantity of mortar used reached 4,000 liters. Due to issues with the mortar preparation used, the 4,000 liters spread had to be removed. In all, 8,000 liters were needed to complete the work, resulting in an additional expenditure of $4.938 million, excluding the cost of the mortar," reads the 130-page document.

Among the other shortcomings noted by the AMP in the Île-aux-Tourtes bridge file are the lack of visits by the MTSM to the worksite, the lack of communication between the various stakeholders, the disappearance and non-reading of certain e-mails, the unavailability of certain documents, and more.

Roxboro Excavation Inc. is part of the consortium formed by Dragados Canada Inc. Roxboro Excavation Inc. and Construction DeMathieu Bard (CDB) Inc. and was awarded the contract to build the new infrastructure, scheduled for partial inauguration in 2026.

The full report is available at https://amp.quebec.

RECOMMANDÉS POUR VOUS


Publié hier à 13h00

Quelques travaux routiers prévus le vendredi 15 mai

Le ministère des Transports et de la Mobilité durable (MTMD) a annoncé la tenue d’entraves mineures dans la région. La route 201 à la hauteur de Rigaud, au sud de l'A40 ainsi qu'à Coteau-du-Lac, au niveau du chemin du Ruisseau Nord, sont concernés. Pour ce qui est de Rigaud, les travaux s'échelonnent de 8 h à 11 h. À Coteau-du-Lac, l’entrave ne ...

Publié le 12 mai 2026

Rencontre virtuelle d'exo sur le nouveau réseau d'autobus La Presqu'Île

Les citoyens de Vaudreuil-Soulanges intéressés à en savoir plus sur la refonte du circuit La Presqu'Île, desservi par exo, et qui entrera en vigueur le 18 mai ont une chance d'en apprendre plus sur le sujet. Une séance d'information virtuelle se tiendra le mercredi 13 mai en soirée en mode virtuel.  La rencontre qui débutera à 18 h 30 et se ...

Publié le 7 mai 2026

Fermeture temporaire de la sortie 41 de l'A-40 est

La sortie 41 de l'autoroute 40 en direction est est la dernière pour rejoindre l'île Perrot via l'autoroute. Celle-ci sera fermée dans la nuit du 8 au 9 mai et une partie de la journée du 9 mai. Selon le ministère des Transports du Québec, cette entrave est rendue nécessaire par le transfert de la voie de desserte de l'autoroute 40 à son ...

app-store-badge google-play-badge